| Run sewer to house |
7:00 AM |
9:00 AM |
Dauenhauer |
| Change out water meter |
7:00 AM |
|
Louisville Water Co. |
| Cut-in road, rock road, back of lot |
9:00 AM |
11:00 AM |
C & W |
| Deliver rock for cut-in road (6 loads "crusher run") |
10:00 AM |
11:00 AM |
Rogers Group |
| Deliver RV's |
10:00 AM |
|
Tom Stinnet RV |
| Move Out |
11:00 AM |
5:00 PM |
L & K |
| Stage Construction Equipment on site |
NOON |
|
C&W |
| Tree Removal and trim trees |
9:00 AM |
11:00 AM |
Bob Ray Co. |
| Install Temp Electric (2 poles) and Inspection |
3:00 PM |
4:00 PM |
Paulin |
| Disconnect Utilities/phone/cable From existing house & hookup site trailer & Temp Pole, Install Electric across driveway |
3:00 PM |
4:00 PM |
EON-US (LG&E) |
| Secure Water Source |
3:00 PM |
|
Elite / L&K Locations |
| Stake House Layout |
4:00 PM |
5:00 PM |
Surveying Services |
| Drain Pool |
4:00 PM |
|
Elite |
| Move existing pole, add transformer, underground, cut driveway for electric |
4:00 PM |
6:00 PM |
EON-US (LG&E) |
| Braveheart check in |
6:30 AM |
7:30 AM |
ABC |
| Braveheart Rush |
7:30 AM |
10:30 AM |
ABC |
| Deliver Dumpsters for Demo |
10:00 AM |
11:00 AM |
Industrial Disposal |
| Braveheart checkout |
10:30 AM |
11:00 AM |
ABC |
| Demo |
11:00 AM |
4:00 PM |
Advanced Paving,
Bob Ray Co. |
| Excavate top layer of ground where house goes + Pavers |
NOON |
1:00 PM |
C&W |
| Gravel Delivery (4) loads #57, (1) load 9's |
NOON |
|
Rogers Group |
| Gravel Delivery for Utilities |
NOON |
|
Dauenhauer |
| Dirt Delivery |
1:00 PM |
|
C&W |
| Dig Footings / Steel Delivery |
1:00 PM |
2:00 PM |
Keith /3N / C&W |
| Sand Delivery for Pool (4 loads) |
1:00 PM |
2:00 PM |
Johnson Construction Materials |
| Install Electric across yard (immediately after Demo) |
1:30 PM |
|
EON-US (LG&E) |
| Form, Rock, and Prep Slab |
1:30 PM |
5:30 PM |
R & R Concrete |
| Footing Inspection |
2:00 PM |
|
3N |
| Deliver Concrete & Pour Footings |
2:00 PM |
3:00 PM |
R & R Concrete / IMI |
| Set Site Office |
2:00 PM |
3:00 PM |
ModSpace |
| Deliver and Set-up VIP Tent |
2:00 PM |
3:00 PM |
Rental Depot |
| Deliver all equipment to site from staging area |
2:00 PM |
|
|
| Deliver all Lumber including Trim to Staging (Except Doors and windows) |
2:00 PM |
7:00 PM |
Boland Maloney |
| Excavate Pool |
3:00 PM |
5:00 PM |
Bob Ray Co. |
| Set-up crane to place pool |
3:00 PM |
|
Suburban Steel |
| Rockslingers on site (4 trucks) |
3:00 PM |
|
Vittitow / T&C Stone |
| Dig Electric to house |
4:00 PM |
5:30 PM |
Paulin Electric |
| Deliver Pool |
4:00 PM |
4:30 PM |
Viking Pools - manufacturer, The Pool Guyz -Delivery
Clearwater Fiberglass Pools and Spas- Installer |
| Plumbing Groundwork, Sewer, Gas, and Water + DRYER VENT - 3" PVC |
4:30 PM |
6:30 PM |
Dauenhauer |
| Floor Plugs and Dig Electric (in Slab) |
5:30 PM |
6:30 PM |
Paulin |
| Run Exhaust Vent for downdraft cooktop in Slab |
5:30 PM |
6:30 PM |
Project / Chris G. |
| Groundwork Inspection |
6:30 PM |
|
Dauenhauer |
| Place the Pool |
7:00 PM |
8:00 PM |
Viking Pools - manufacturer, The Pool Guyz -Delivery
Clearwater Fiberglass Pools and Spas- Installer |
| Deliver Concrete Pumps (2 pumps) |
7:00 PM |
8:00 PM |
Gladiator |
| Deliver Concrete & Pour Slab |
8:00 PM |
10:00 PM |
R & R Concrete / IMI |
| Backfill Pool |
9:00 PM |
10:00 PM |
TCB |
| Cure time |
10:00 PM |
1:00 AM |
|
| Deliver Concrete & Pour GARAGE Slab |
11:30 PM |
12:30 AM |
R & R Concrete / IMI |
| |
|
|
|
| Strip Forms |
1:00 AM |
2:00 AM |
R & R Concrete |
| Backfill foundation and grade |
2:00 AM |
3:00 AM |
TCB |
| Stage cranes for framing |
3:00 AM |
|
Padgett |
| Snap Lines |
3:00 AM |
4:00 AM |
Framers (4) TOM BANNISTER |
| Start Framing |
4:00 AM |
4:00 PM |
Framers |
| Set First floor wall panels |
4:00 AM |
7:00 AM |
Framers |
| Set Roof Trusses |
6:00 AM |
12:00 Noon |
Framers |
| Deliver Shingles/Ice Guard/Nails/Felt Paper, Roof Vents/Metal Flashing |
6:30 AM |
|
Shelter |
| Install Tyvek |
7:00 AM |
8:00 AM |
Framers |
| Deliver Doors and Windows |
7:00 AM |
|
Boland Maloney |
| Install Ext Doors and Windows |
8:00 AM |
10:00 AM |
Framers |
| Termite treatment |
8:00 AM |
9:00 AM |
Envirosafe Pest Control |
| Install Roof Sheathing & Felt Paper |
10:00 AM |
1:00 PM |
Framers |
| Delivery of rough Plumbing material |
10:00 AM |
|
Dauenhauer |
| Plumbing Rough |
11:00 AM |
5:00 PM |
Dauenhauer |
| Deliver and Rough HVAC Start |
11:00 AM |
5:00 PM |
Project |
| Deliver DGA - 240 tons of DGA for Drive, Start Rocking and Compacting Drive |
NOON |
|
Rogers Group |
| Deliver Cornice |
NOON |
|
Boland Maloney |
| Install Cornice |
NOON |
3:00 PM |
Framers |
| Design Producer Electrical Walkthrough Framing punch, backing, and blocking |
NOON |
1:00 PM |
Paulin |
| Install Shingles |
NOON |
4:00 PM |
New Level |
| Layout and mark job for Brick |
NOON |
2:00 PM |
Eddie Greenwell and Barry |
| Deliver Gable Vents (FRAMERS INSTALL) |
NOON |
|
Bob Fullen |
| Deliver Sand for Pavers |
1:00 PM |
|
Johnson Construction Materials |
| Rough Electric |
1:00 PM |
9:00 PM |
Paulin |
| TV, Tele, Security, Speakers |
1:00 PM |
9:00 PM |
Super Home Systems |
| Deliver Brick, Sand, Lintels, everything |
1:00 PM |
|
Bleuel |
| Rock and Compact Drive and rear patio for PAVERS |
2:00 PM |
|
Various |
| Start Brick |
2:00 PM |
12:00 Midnight |
Nico & New Level as reinforcements |
| Deliver Fireplace & Install |
3:00 PM |
4:00 PM |
Fireplace Dist |
| Install metal in gables |
3:00 PM |
4:00 PM |
New Level |
| Start stucco in gables |
4:00 PM |
|
Julius Schnurr and Sons |
| Build Electric Service |
5:00 PM |
6:00 PM |
Paulin |
| Ray Sandbek Inspection |
8:00 PM |
9:00 PM |
Sevice USA |
| Mechanical Inspection and Framing Inspection |
9:00 PM |
10:00 PM |
City of Lou |
| Deliver & Install Wall Insulation |
10:00 PM |
12:00 Midnight |
Sexton Insulation |
| Deliver Drywall & Mud, corner bead, etc |
10:00 PM |
11:00 p.m |
Metro Materials |
| Stage Temp Heat & Drying Equipment |
10:00 PM |
|
Preventec |
| Hang Drywall & Finish |
11:00 PM |
12:00 Noon |
Builders Choice |
| Clean up Brick & Rough Grade |
12:00 midnight |
1:00 AM |
TCB |
| Deliver Concrete & Pour Exterior Concrete (porches and around pool) |
1:00 AM |
7:00 AM |
R & R Concrete / IMI |
| Deliver Hardscape Matl (Pavers), and make sure sand and DGA on site |
6:00 AM |
|
Belgard |
| Install Hardscape (Pavers) |
7:00 AM |
7:00 PM |
Various |
| Deliver & Wrap cornice and Porch Ceilings |
7:00 AM |
3:00 PM |
Various |
| Deliver Paint |
10:00 AM |
|
Sherwin Williams |
| Deliver and Install Pool Equipment |
10:00 AM |
11:00 AM |
The Pool Guyz - installer, Viking - Manufacturer |
| Deliver and Install Landscaping |
10:00 AM |
6:00 PM |
Wade Wearren |
| Prime Drywall, Bathrooms first |
11:00 AM |
2:00 PM |
Builders Choice |
| Design Producer Paint and Tile Walkthru |
11:00 AM |
12:00 Noon |
|
| Prime walls and paint ceilings |
NOON |
2:00 PM |
Builders Choice |
| Deliver Tile |
NOON |
|
Commercial Flooring |
| Start Tile - Bathrooms First (but do not do floor in M. Bath vanity area or Laundry area until cabinets come in at 2:00 PM) |
1:00 PM |
9:00 PM |
Commercial Flooring |
| Deliver Interior Trim and Doors |
1:00 PM |
|
Boland Maloney |
| Deliver Cabinets |
1:00 PM |
|
Kraftmaid / PC Bld Matl |
| Start Termination in Garage Closet |
2:00 PM |
4:00 PM |
Hitcents |
| Start Trim |
2:00 PM |
12:00 Midnight |
Trim Carpenters |
| Install Cabinets |
2:00 PM |
8:00 PM |
PC Bld Matl |
| Delivery and Install of Fireplace Surround |
2:00 PM |
3:00 PM |
|
| Delivery and Install Vents |
2:00 PM |
3:00 PM |
Project |
| Deliver and Install Gutters |
3:00 PM |
5:00 PM |
Sexton Gutters |
| Measure for Shower Doors |
3:00 PM |
4:00 PM |
AG Glass |
| Measure for Screen Porch |
4:00 PM |
5:00 PM |
A-1 Aluminum |
| Deliver Granite Tops |
7:00 PM |
|
Bella |
| Install Granite Tops |
8:00 PM |
10:00 PM |
Bella |
| Install Tile Backsplash (in guest suite) |
10:00 PM |
12 :00 midnight |
Todd Dahlgren Don Skaggs Mike Francis |
| Paint Interior Trim, Walls (paint Bathrooms first for Plumbing Finish) |
10:00 PM |
6:00 AM |
Builders Choice |
| |
|
|
|
| Need 4 or 5 painters all day on 12th |
|
|
Builders Choice |
| Deliver Door Hardware |
7:00 AM |
|
Emtek |
| Deliver Finish Plumbing Material & Start finish |
7:00 AM |
1:00 PM |
Dauenhauer |
| Install Door Hardware / Lockout / Loose ends |
7:00 AM |
10:00 AM |
Trim Carpenters |
| Hookup AC Units |
8:00 AM |
10:00 PM |
Paulin Electric |
| Deliver Appliances |
8:00 AM |
|
Sears |
| HVAC Startup |
8:00 AM |
9:00 AM |
Project |
| Finish Grade |
8:00 AM |
10:00 AM |
TCB |
| Set A/C unit |
8:00 AM |
10:00 AM |
Project |
| Startup Fireplace Logs |
8:00 AM |
9:00 AM |
Fireplace Dist |
| Deliver Light Fixtures (SOME DECORATIVE FIXTURES WILL BE HUNG ON TUESDAY OR WEDNESDAY) |
10:00 AM |
|
Rueff Lighting |
| Electric Finish |
10:00 AM |
4:00 PM |
Paulin |
| TV, Tele, Security, Speakers/Automation |
10:00 AM |
2:00 PM |
Super Home Systems/Hit Cents |
| Deliver and Install Screen Porch |
NOON |
2:00 PM |
A-1 Aluminum |
| Install Appliances |
2:00 PM |
3:00 PM |
Dauenhauer / Paulin |
| Deliver Hardwood |
4:00 PM |
|
Lumber Liquidators |
| Install Hardwood |
5:00 PM |
3:00 AM |
Various |
| Deliver and Install Garage door |
5:00 PM |
7:00 PM |
Action Overhead |
| Start Irrigation and Landscape Lights |
5:00 PM |
1:00 AM |
Evergreen Irrigation |
| Deliver and Install Fence at Pool |
6:00 PM |
10:00 PM |
Raatz |
| Deliver & Install Mirrors, Shower Doors, Bath Hardware |
3:00 AM |
8:00 AM |
AG Glass |
| Deliver and Install Closet Systems |
3:00 AM |
8:00 AM |
AG Glass |
| Install Shoemold at all hardwood areas (Will be on site delivered with trim package and stored away) |
6:00 AM |
8:00 AM |
Trim Carpenters |
| Deliver Sod |
6:00 AM |
7:00 AM |
Mason Valley |
| Install Sod (Start in Front yard) |
6:00 AM |
11:00 AM |
Mason Valley |
| Finish and Telephone and TV if necessary |
7:00 AM |
8:00 AM |
Super Home Systems/Hit Cents |
| Final Clean and pressure wash pavers |
8:00 AM |
12:00 Noon |
Time to Clean |
| Clear site, cleanout garage, sweep streets |
8:00 AM |
until done |
Volunteers |
| Install any remaining light fixtures |
THROUGHOUT DAY, SOME
HAVE TO BE DONE AFTER FURNITURE
|
|
|
| Turn over garage to designers |
9:00 AM |
|
|
| Final Clean Touch-up |
9:00 AM |
1:00 PM |
Time to Clean |
| Paint Touch-up (Painters all day) |
10:00 AM |
Whenever |
Builders Choice |
| Final Inspect / CO |
10:00 AM |
11:00 AM |
City of Lou |
| Insight Cable and Tele Connect |
10:00 AM |
NOON |
Insight |
| Startup Irrigation |
11:00 AM |
12:00 Noon |
Evergreen Irrigation |
| HAND OVER KEYS |
2:00 PM |
2:00 PM |
|
| Restricted Access |
2:00 PM |
|
|
| House numbers |
3:00 PM |
3:30 PM |
|
| Electrical Design fixture install |
5:00 PM |
7:00 PM |
|
| Punch-out |
6:00 PM |
until done |
Builders Choice / Elite |
| Punch Out, |
6:00 PM |
till complete |
|
| Insight Final install |
7:00 PM |
9:00 PM |
|
| Plasma TV install PLUS TESTING |
7:00 PM |
9:00 PM |
Super Home Systems/Hit Cents |
| Install Mini Blinds |
7:00 PM |
10:00 PM |
|
| |
|
|
|
| move materials and clean site |
7:00 AM |
Noon |
|
| 2 - 4 trim carpenters |
7:00 AM |
Noon |
|
| 5 Painters |
7:00 AM |
Noon |
|
| 2 Electricians |
7:00 AM |
Noon |
|
| 2 Landscapers |
7:00 AM |
Noon |
|
| 2 HVAC Techs |
7:00 AM |
Noon |
|
| 2 Plumbers |
7:00 AM |
Noon |
|
| Cleaners |
7:00 AM |
2:00 PM |
Time to Clean |
| Deliver and Blow Attic Insulation |
7:00 AM |
8:00 AM |
Sexton Insulation |
| Street Sweep |
9:00 AM |
NOON |
Mangum Enterprise (955-9422) |
| Volunteers to clean site |
9:00 AM |
2:00 PM |
Volunteers |
| Move that bus! |
2:00 PM |
|
|
| Clean Up |
9:00 AM |
|
|
| Day 10 and Beyond |
| REMOVE TEMPORARY DRIVE |
|
|
|
| FINISH GRADE |
|
|
|
| SOD |
|
|
|
| |
|
|
|
| Footing Inspection |
2:00 PM |
|
3N |
| Groundwork Inspection |
6:30 PM |
|
Dauenhauer |
| Ray Sandbek Inspection |
8:00 PM |
9:00 PM |
Sevice USA |
| Mechanical Inspection and Framing Inspection |
9:00 PM |
10:00 PM |
City of Lou |
| Final Inspect / CO |
10:00 AM |
11:00 AM |
City of Lou |